of valves and fittings installed in the line . Where the measurement terminates <br /> at a valve , bend , tee , or other fitting , the centerline of the valve or fitting shall <br /> be the point of termination . All required pipe lining , coating , encasement <br /> material ( remove see "J " below) , restraining devices , and thrust blocks shall <br /> be included in the cost of the pipe . <br /> C . Fittings : Measurement of cast iron and ductile iron fittings shall be on the <br /> basis of weight ( in tons ) . The weights used to determine the quantity <br /> installed shall be the weights of the appropriate fittings as listed in the <br /> supplier' s invoice or catalog . When mechanical joint fittings are required , the <br /> weight of the gland bolts and gaskets shall not be added to the listed weight <br /> of the fittings . Where flanged fittings are furnished , the weight of the bolts <br /> and gaskets shall not be included . <br /> D . Gate Valves and Tapping Valves : Measurement shall be on the basis of <br /> furnishing and installing each type and size of valve (and tapping sleeve , if <br /> applicable) required , including the valve box, cover, and other associated <br /> items . <br /> E . Fire Hydrant Assembly : Measurement of fire hydrant assembly shall be for <br /> the actual number (each ) constructed in accordance with the Plans and <br /> Specifications , or as directed by the Engineer, at the unit price bid for the item <br /> " Fire Hydrant Assembly, " scheduled in the Form of Proposal . The unit price <br /> for " Fire Hydrant Assembly" shall include cutting bituminous paving , removal <br /> of paving courses and curb if required , excavation , furnishing and installation <br /> fe of 10 ' (6" ) D . I . P . water main , dry-barrel traffic hydrant , concrete foundations <br /> for hydrant , fitting , tapping sleeve and valve if required , one ( 1 ) 6 " diameter <br /> gate valve , concrete thrust block (reaction backing ) for fire hydrant, backfill , <br /> blue reflective markers , all materials , equipment, labor and all else necessary <br /> therefore and incidental thereto . All areas shall be restored to equal or better <br /> condition as determined by the Engineer. <br /> F . Water Service : Measurement of service connections for payment shall be for <br /> each service installed either short or long or single or double . Measurement <br /> of water service lateral shall include furnishing and construction of piping and <br /> appurtenances to carry and distribute water from the water main to the edge <br /> of the Right-of-Way for future service to individual property owners . The work <br /> shall include , but shall not be limited to , cutting of existing pavement where <br /> required , jack and bore of existing pavement where required , sleeve , <br /> excavation , installation (of pipe , meter boxes , connections and associated <br /> appurtenances ) , backfilling , testing , disinfection , and all restoration in kind . <br /> The services shall be of a type and size specified , and shall be constructed in <br /> accordance with these Plans and Specification , or as directed by the <br /> Engineer. <br /> G . PE Horizontal Directional Bore : Measurement for payment for directional <br /> bore shall be per linear foot for each size installed . Measurement of PE <br /> horizontal directional bore shall include all material ( including each size PE <br /> pipe ) , equipment , supplies , fuel , labor, sheeting and bracing , jacking and <br /> boring pits ( if required ) , excavation , dewatering , backfilling , compaction , <br /> mechanical fittings , restoration , furnishing and installing PE pipe . Wedge type <br /> 01025-2 <br /> F :\Utilities\UTILITY - ENGINEERING\Projects - Assessment Projects\West Side Subdivision - UCP#2177\Bid <br /> docs\specs\01025 Measurement and Payment.doc <br />