Laserfiche WebLink
SECTION 01153 <br /> CHANGE ORDER PROCEDURES <br /> PART 1 -- GENERAL <br /> 1 .01 REQUIREMENTS INCLUDE <br /> A. Promptly implement Change Order Procedures <br /> 1 . Provide full written data required to evaluate changes . <br /> 2 . Maintain detailed records of work done on a time-and- <br /> material/force account basis . <br /> 3 . Provide full documentation to Engineer on request . <br /> B . Designate in writing the member of Contractor' s organization : <br /> 1 . Who is authorized to accept changes in the Work <br /> 2 . Who is responsible for informing others in the contractor's employ <br /> of the authorization of changes in the Work. <br /> C . Owner will designate in writing the person who is authorized to execute <br /> Change Orders . <br /> 1 .02 RELATED REQUIREMENTS <br /> A. The amount of established unit prices. <br /> B . Conditions of the Contract: <br /> 1 . Methods of determining cost or credit to owner resulting from <br /> changes in Work made on a time-and-materials basis . <br /> 2 . Contractor' s claims for additional costs . <br /> C . Section 01152 : Applications for payment. <br /> D . Section 01311 : Construction schedules . <br /> E . Section 01370 : Schedule of Values. <br /> F . Section 01720 : Project Record Documents . <br /> 1 .03 DEFINITIONS <br /> A . Change Order: See General Conditions <br /> 01153 Change Order Procedures.doc <br /> 01153 - 1 <br /> J:\07-029 12 Inch WM - Vero Lake EstatesVocumenls\Reports\Bidding Contract Specifications\01153 Change Order Procedures.doc <br />