IRCJ DORMITORY TIME EXTENSION ANALYSIS <br /> Project: Indian River County Jail Expansion <br /> Contractor. Peter R Brown Construction Company, Inc <br /> Architect: Clemons Rutherford & Associates, Inc <br /> Original Substantial Completion 5/18/2007 <br /> New Substantial Completion 8/3/2007 <br /> SUMMARY: <br /> TOTAL DAYS IMPACTED: 77 Original Substantial Completion date for the Dormitory Buildings was May 18, <br /> 2007 now Substantial Completion scheduled for August 3, 2007 Due to <br /> weather conditions, which were believed could be overcome, and unforeseen <br /> modifications to the fire alarm system and fencing, in which additional work was <br /> required, the project experienced unfortunate and unavoidable delays . <br /> May- 07 <br /> DAYSIMPACTED: 16 <br /> WEATHER: 2 Days of rain greater than 114 inch . Delayed Dormitory Canopy and Fencing <br /> 1 Days of recovery due to heavy amounts of min <br /> UNFORESEEN CONDITIONS: 13 Fire Marshal mandated 56 additional smoke detectors installed in the dormitory <br /> buildings to complywith local jurisdiction codes Work extended into June. <br /> June - 07 <br /> DAYSIMPACTED: 30 <br /> WEATHER: 3 Days of rain greater than 114 inch . Delayed Dormitory Fencing and Concrete <br /> Fence Aprons <br /> 1 Days of recovery due to heavy amounts of rain <br /> UNFORESEEN CONDITIONS: 26 Fire Marshal mandated 56 additional smoke detectors installed in the dormitory <br /> buildings to comply with local jurisdiction <br /> July- 07 <br /> DAYSIMPACTED: 31 <br /> WEATHER: 2 Days of rain greater than 114 inch Delayed Dormitory Fencing and Concrete <br /> Fence Aprons <br /> 2 Days of recovery due to heavy amounts of rain <br /> UNFORESEEN CONDITIONS: 27 Fencing modifications necessary to coordinate existing fencing conditions with <br /> new fencing layout . <br /> Page 5 of 8 <br />