IRC JAIL INTAKE BUILDING TIME EXTENSION ANALYSIS <br /> Project: Indian River County .Jail Expansion <br /> Contractor. Peter R Brown Constructlon Company, Inc <br /> Architect: Clemons Rutherford & Associates, Inc <br /> Original Substantial Completion 511812007 <br /> New Substantial Completion SM7/2007 <br /> SUMMARY: <br /> TOTAL DAYS IMPACTED: 91 Original Substantial Completion Date for Intake Building was May 18, 207 <br /> Substantial Completion now August 17 2007 Due to weather conditions, which <br /> were believed could he overcome, and unforeseen existing conditions and <br /> utilities in which additional work was required, the project experienced <br /> unfortunate and unavoidable delays <br /> June -06 <br /> TOTAL DAYS IMPACTED: 7 <br /> WEATHER: 4 Days of rain greater than 1/4 Inch Directly affected Warehouse activities which <br /> "rescheduled to occur before intake building work was to begin Delayed <br /> Intake Demolition and Building pad . <br /> 3 Days of recovery due to heavy amounts of rain <br /> July- 06 <br /> TOTAL DAYS IMPACTED: 8 <br /> WEATHER: 5 Days of rain greater than 114 inch Directly affected Warehouse activities which <br /> were scheduled to occur before intake building work was to begin Delayed <br /> Intake Building Pad, Footings. and Slab. <br /> 3 Days of recovery due to heavy amounts of rain <br /> August- 06 <br /> TOTAL DAYS IMPACTED: 13 <br /> WEATHER: 8 Days of rain greater than 114 inch. Delayed Intake Footings and stab <br /> 2 Days of recovery due to heavy amounts of rain and preparation and clean up for <br /> expected Hurricane <br /> UNFORESEEN CONDITIONS: 5 Asbestos Survey required by Subcontractor prior to performing demolition . Due <br /> to year of original construction Survey was not expected . Delayed Intake <br /> Demolition . <br /> Page 1 of 8 <br />