IRC JAIL INTAKE BUILDING TIME EXTENSION ANALYSIS <br /> September- 06 <br /> DAYSIMPACTED: 19 <br /> WEATHER: 7 Days of rain greater than 114 inch . Delayed Intake Footings and Slab <br /> 2 Days of recovery due to heavy amounts of rain <br /> UNFORESEEN CONDITIONS: 10 RFIs 77, 82 and 85 Unforeseen existing utilities In footings and slab of Intake <br /> Building Existing utilities included gas, water, electric, data and added new fire <br /> sprinkler line to keep sprinklers in Kitchen Building operational . Required repair <br /> andfor relocation of utilNes. Delays extended Into October. Delayed Intake <br /> Footings and slab <br /> October-06 <br /> DAYSIMPACTED: 4 <br /> WEATHER: 1 Days of rain greater than 114 inch Delayed Intake Footings and Slab <br /> 0 <br /> UNFORESEEN CONDITIONS: 3 Unforeseen water line In new Intake footing hill during footing excavation <br /> Delayed Intake Footings and Slab , <br /> November-06 <br /> DAYSIMPACTED: 0 <br /> WEATHER: 0 <br /> 0 <br /> December- 06 <br /> DAYSIMPACTED: 0 <br /> WEATHER: 0 <br /> D <br /> January-07 <br /> DAYSIMPACTED: 0 <br /> WEATHER: 0 <br /> 0 <br /> Page 2 of 8 <br />