• individual components to be installed , street closure dates and durations including <br /> the start and completion dates of each phase. <br /> In addition to the CPM schedule for the BASE BID — TIMEFRAME, the Contractor <br /> shall submit, in narrative format, a detailed description of the means and methods <br />,. for the Contractor's work including but not limited to the mobilization and <br /> demobilization of all equipment and materials , the demolition sequencing of the <br /> work, the individual phasing sequencing of each component manufacturing and <br /> installation , the Contractor's proposed manpower and equipment allocations and <br /> commitments for each phase of the work, the Contractor's proposed work hours for <br /> each day to be worked , the phasing of road closures with their closure dates and <br /> durations , work sequence and days of the week the Contractor and his <br /> subcontractors will require from the City to complete the work within the time frames <br /> of the BASE BID — TIMEFRAME . <br /> The CPM schedules for the BASE BID — TIMEFRAME and narrative approach for <br /> the project will be used by the City in determining the best value in awarding the <br /> construction contract. <br /> The contractor will not be allowed to change his submitted CPM schedule for the <br /> BASE BID — TIMEFRAME prior to and or after the Award of Contract and the Notice <br />,w to Proceed is issued by the City/County without prior written approval of the <br /> City/County's Project Manager. <br /> (2) The Contractor shall provide daily clean up of the project work area . Cleanup shall include <br /> but not be limited to removal of trash , construction debris , excavated materials and materials <br /> generated as a result of the demolition of the existing sidewalks, curbs and gutters , road way <br /> components . <br /> (3) The Contractor shall restore all roadways immediately upon the completion of each segment <br /> and or phase of the construction . Such restoration shall be to the satisfaction of the City/County. <br /> (4) The Contractor shall submit for the City/County review and approval , as part of his bid <br /> submission , a sample copy of his company's daily reporting format for reporting the progress of <br />,. construction . This format shall include but not be limited to the detailing of all labor, equipment and <br /> materials used in the construction of the project along with the areas worked , type of work <br /> performed , problems encountered and daily weather conditions at the work areas. The Contractor <br /> a will be required to submit to the City/County's Project Manager, copies of all daily reports completed <br /> by the Contractor's personnel and his subcontractors at the beginning of the following work day for <br /> each day worked . <br /> (5) The Contractor shall be required to submit (2) copies of 8 1 /2"x 11 " progress color photos <br /> indicating the completion of the contract work with the dates that the work was performed , on a <br /> weekly basis to the City's Project Manager. The Contractor shall also be required to submit as-built <br />+� surveys, by a registered land surveyor licensed to do work in the State of Florida , on a weekly basis <br /> to the City's Project managerthat indicate the completion of contract work by the Contractor and his <br /> subcontractors . <br /> (6) The Contractor shall provide as part of the contract work , adequate sanitary facilities , within <br /> the fenced-in areas of the total project area , for the use of the Contractor's workmen . <br /> 56 <br /> W2M9:5429AM <br />