Laserfiche WebLink
C. If the completion of any activity, whether or not critical, falls more than 100 percent <br />behind its approved duration, the Contractor shall submit for approval a schedule <br />adjustment showing each such activity divided into two activities reflecting completed <br />versus uncompleted work. <br />D. Shop drawings which are not approved on the first submittal or within the scheduled time <br />shall be immediately rescheduled, as well as pipelines and tanks which do not pass leak <br />tests. <br />E. The contract completion time will be adjusted only for causes specified in this contract. <br />In the event the Contractor requests an extension of any contract completion date, he <br />shall furnish such justification and supporting evidence as the Engineer may deem <br />necessary for determination as to whether the Contractor is entitled to an extension of <br />time under the provisions of the contract. Engineer will, after receipt of such justification <br />and supporting evidence make findings of fact and will advise the Contractor in writing <br />thereof. If the Engineer finds that the Contractor is entitled to any extension of any <br />contract completion date under the provisions of this contract, the Engineer's <br />determination as to the total number of days of extension shall be based upon the <br />currently approved schedule and on all data relevant to the extension. Such data shall be <br />included in the next monthly updating of the schedule. The Contractor acknowledges and <br />agrees that actual delays in activities which, according to the schedule, do not affect any <br />contract completion date shown by the critical path in the schedule do not have any affect <br />on the contract completion date or dates, and therefore, will not be the basis for a change <br />therein. <br />F. From time to time it may be necessary for the contract schedule and/or completion time <br />to be adjusted by the Engineer to reflect the effects of job conditions, weather, technical <br />difficulties, strikes, unavoidable delays on the part of the Owner or his representatives, <br />and other unforeseeable conditions which may indicate schedule adjustments and/or <br />completion time extension. Under such conditions, the Contractor shall reschedule the <br />work and/or contract completion time to reflect the changed conditions and the <br />Contractor shall revise his schedule accordingly. No additional compensation shall be <br />made to the Contractor for such schedule changes except for unavoidable overall contract <br />time extensions beyond the actual completion of all unaffected work in the contract, in <br />which case the Contractor shall take all possible action to muun ize any time extension <br />and any additional cost to the Owner. It is specifically pointed out that the use of <br />available float time in the schedule may be used by the Owner as defined by the <br />Engineer, as well as by the Contractor. Float time is defined as the amount of time <br />between the early start date, and the late start date, or the early finish date and the late <br />finish date, of any of the activities in the schedule. <br />G. The Owner controls the float time in the approved schedule and , therefore, without <br />obligation to extend either the overall completion date or any intermediate completion <br />dates set out in the schedule, the Owner may initiate changes to the contract work that <br />absorb float time only. Owner -initiated changes that affect the critical path on the <br />approved schedule shall be the sole grounds for extending (or contracting) said <br />completion dates. Contractor -initiated changes that encroach on the float time identified <br />in the approved schedule may be accomplished with the Owner's concurrence. Such <br />changes, however, shall give way to Owner -initiated changes competing for the same <br />float time. <br />044572017 <br />01311-4 <br />